PROPOSED IMPROVEMENTS

  • Eight-foot sidewalk on the south side of Lafayette Street from the east side of Seminole Drive to Winchester Lane excluding the intersection at Lafayette Street and Magnolia Drive because the intersection improvements at this location have been completed as a separate Capital Improvement project.
  • Adding turn lanes at three locations on the east side of Magnolia Drive to enhance safety and facilitate the turning movements to the access road and businesses.
  • Landscaping
  • Stormwater Drainage System associated with the sidewalk reconstruction and turn lane additions
  • 800 feet of Road Reconstruction from Seminole Drive toward east.

PROJECT SCHEDULE:

  • Design Phase from March 2013 through October 2013
  • Construction Phase from January 2014 through June 2014
CONSTRUCTION PHASES AND SCHEDULE

Segment 1 - From Seminole Dr. to 300 Feet East (Eastern Driveway of The Moon)

Open

Segment 2 - From 300 Feet East of Eastern Driveway of The Moon to Cabo's Restaurant (Access Drive to Parkway Shopping Center)

Open

Segment 3 - From Access Drive of Parkway Shopping Center to 250 east

Open

Phase III East of Magnolia to Indian Head Dr.

From April 8, 2014 to July 31, 2014

Detour Map

FUTURE EVENTS
Lafayette Street Improvements -Phase 3 Construction Progress Monthly Meeting

WHEN: Thursday June 26, 2014 at 5:30 PM
WHERE: 1001 DeSoto Park Drive (The Governor Martin House at the B. Calvin Jones Center for Archaeology)

PAST EVENTS

  • Maintenance of Traffic Plan Review Meeting
    Date: August 15, 2013
    Time: 9:00 a.m. to 11:00 a.m.
    Location: 1001 DeSoto Park Drive (The Governor Martin House) 
     
  • Public Open House Meeting
    Date: August 22, 2013
    Time: 6:00 p.m. to 7:30 p.m.
    Location: Florida Department of Transportation’s Auditorium (605 Suwannee Street) 
     

PROJECT CONTACTS:

Chris Muehlemann, P.E., Project Manager
Leon County Department of Public Works
2280 Miccosukee Road, Tallahassee, FL 32308 
Email: MuehlemannC@leoncountyfl.gov 
Phone: (850) 606-1536      Fax: (850) 606-1501

Charles Wu, P.E., Chief of Engineering Design
Leon County Department of Public Works
2280 Miccosukee Road, Tallahassee, FL 32308 
Email: WuC@leoncountyfl.gov 
Phone: (850) 606-1546      Fax: (850) 606-1501